What do I do with the electricity produced that I don’t consume?
In order to do so you must first fill out a Smart Export Guarantee (“SEG”) application form. Download the form from your local electricity provider (e.g., British Gas, EDF Energy) website. Please note that as part of the application process you will need to submit the following information and documentation:
Your MPAN number
A copy of your Microgeneration Certification Scheme (MCS) certificate; this comes to you directly from MCS about one month after your system is commissioned.
Proof of connection to the grid (e.g., G83, G59 certificate)
Proof of commissioning (e.g., commissioning certificate) - can be found in the handover pack provided to you at the end of the installation
Proof of system ownership (e.g., your Otovo invoice) - can be found in the handover pack provided to you at the end of the installation
Any other documents as required by the electricity provider